Monami Construction have commenced the Enabling Works to the Becton Dickinson Research Centre, National Technology Park, Plassey, Limerick.

The project consists of the following works:

  • Strip out of the existing reception and restaurant area
  • Excavation of the main building area down to formation level
  • Remedial works as required to foundations & external walls
  • Installation of new undefloor drainage and ground floor slab
  • Remedial works as required to the roof
  • Fit out to provide offices and production area including new mechanical and electrical installation
  • External works including fencing and low level hedging to enclose the site, gated access, drainage, new substation, docking
    area, etc.

The project has a programme of 8 weeks with a completion date early March 2017