Hollystown Pyrite Remediation, Dublin

Hollystown Pyrite Remediation Works, Hollystown, Dublin

Project Description:

Pryrite Remediation Works to 80 housing units at the Chapelwood & Alderwood Housing Estates, Hollystown, Co. Dublin.
The Pyrite Remediation works consisted of the removal and replacement of defective granular sub-fill from existing dwellings, with the subsequent refurbishment and fit out of the entire ground floor and affected areas on the 1st floor.
Works include full strip out and demolition of existing units, removal of the existing ground floor slab, excavation and replacement of defective stone fill from substructures, full reinstatement of substructures and concrete slabs, internal walls, ceilings, joinery, and finishes.
Externally works include excavation of stone fill from the house perimeter and reinstatement of bitmac surfacing, paving and landscaping works.
To date over 60 units have been completed within the agreed time frame of 14 weeks per unit with all works completed to a very high standard of finish.
Project Value:
€1,800,000.00 (to date)

Client:
OSG

Structural Engineer:
Aidan O’ Connell & Associates

Project Duration:
24 months (On Going)

Skills

Posted on

December 5, 2014