Phase 2 of Dromoland Castle Upgrade Works Commences

Phase 2 of Dromoland Castle Upgrade Works Commences

Monami Construction have commenced Phase 2 of the Dromoland Castle Upgrade Works. this will be the 2nd phase out of a total of 4 phases between 2016-2019 that Monami Construction will complete. Phase 2 will consist of the following works:

  • Refurbishment of Terrace Room to include new air conditioning and double glazing to windows.
  • Construction of Energy Centre, Main Distribution Pipework and associated gas compound.
  • Refurbishment of Castle Bedrooms and en-suites and all associated common areas (Stage 1)
  • Upgrade of mechanical and electrical services of Castle ground floor public areas including Gallery, Dining Room, Cocktail Bar and Lounge and male toilets.
  • Refurbishment works to windows on lakeside of Castle and Link Bedrooms.
  • Stone Façade Repair Works to Tower and on lakeside of Castle

Phase 2 has a completion date of April 2017