Monami appointed as Main Contractors for Phase 2 & 3 of Rathborne Remedial Works

Monami appointed as Main Contractors for Phase 2 & 3 of Rathborne Remedial Works

Monami Construction have been appointed as Main Contractors for the Rathborne Phase 2 & 3 Remedial & Repair Works, Ashtown, Dublin 15.

The project will consist of the following:

  • Remedial & Repair Works to 11 nr stand alone apartment blocks including but not limited to the following:
    • Fire proofing works in apartment corridors.
    • Works around windows internally & externally
    • Repairs to fire doors in common area corridors including behind architraves.
    • Upgrade and replacement works to the fire alarm and emergency lighting systems,  including installation of new sounders in bedrooms.
    • Fire proofing coat to all structural steel beams
    • Fire proofing around pipework in basement and service risers
    • Remedial works in basements including new insulation, lighting & services
    • Internal upgrade works throughout
    • External repairs to facades & balconies.
    • Repairs to the boundaries / environs & basement areas.
    • Roof repairs

The project is due to commence in January 2017 will be completed on an 10 month programme