Monami Construction have commenced the Enabling Works to the Becton Dickinson Research Centre, National Technology Park, Plassey, Limerick.
The project consists of the following works:
- Strip out of the existing reception and restaurant area
- Excavation of the main building area down to formation level
- Remedial works as required to foundations & external walls
- Installation of new undefloor drainage and ground floor slab
- Remedial works as required to the roof
- Fit out to provide offices and production area including new mechanical and electrical installation
- External works including fencing and low level hedging to enclose the site, gated access, drainage, new substation, docking
area, etc.
The project has a programme of 8 weeks with a completion date early March 2017